Question 1. What does the Assignments Page in Primavera P6 display?
A. Details of resource assignments to activities
B. Baseline variances for the schedule
C. Critical path activities
D. Float distribution across tasks
Multiple ChoiceScheduling Project
Question 2. What is the purpose of comparing the scheduled finish date to the must finish by date in Primavera P6?
A. Monitor the project timeline against deadlines
B. Adjust resource assignments automatically
C. Recalculate the project baseline
D. Update the critical path dynamically
Multiple ChoiceDeveloping a project
Question 3. Which action allows you to assign activity codes to multiple activities simultaneously?
A. Select the activities on the Activities page, then choose Row Actions/Context → Assign → Codes.
B. Open Calendar Settings and assign the activity codes.
C. Open Project Preferences and assign the activity codes.
D. Open Baseline Manager and assign the activity codes.
Multiple ChoiceScheduling Project
Question 4. What is the function of the relationship lines in the Gantt chart?
A. Visually connect tasks based on their dependencies
B. Highlight activities with float
C. Display tasks grouped by resource type
D. Assign project calendars dynamically
Multiple ChoiceManaging project risks and issues
Question 5. Where can project issues be created and managed in Primavera P6?
A. Issues Workspace > Manage Issues
B. Activities Page > Issues Tab
C. Dashboards > Issues Overview
D. Tools > Project Issues